CMB were awarded the MEP contract for Project Porth under Main Contractor, Andrew Scott and Developers, Trebor. This part of the project consisted of fitting out all of the Mechanical and Electrical systems within the office accommodation of KLA’s new R&D and manufacturing centre in Newport.


We commenced work on the project in March of last year and after 14 months, we are delighted to have successfully handed over the building to a satisfied client.


Some of the works our team and supply chain have carried out include:


·         VRF Systems

·         Ventilation Systems

·         Domestic Water and Sanitary Systems

·         Cold Water Storage Tanks and Booster sets

·         Air Handling Plant

·         Kitchen Supply and Extract Ventilation

·         Fan Coil Units

·         Thermal Insulation

·         Rainwater Harvesting

·         Sprinkler and Hydrant Systems

·         Dry Risers

·         BMS Control System

·         Smoke Control System

·         Above Ground Drainage

·         Gas Supply

·         HV and LV Installation

·         Data Systems

·         PV System

·         Lighting and Controls

·         Emergency Lighting

·         Fire Alarm

·         Earthing and Lightning Protection

·         EV Chargers


Work will now continue to progress on the KLA R&D and manufacturing section of the project where CMB are carrying out the specialist Cleanroom fit out works.


Our team of staff and subcontractors have made good progress so far and we look forward to sharing the latest pictures and update on this soon.