Following April’s successful handover of the specialist Cleanroom Fitout for the KLA R&D and Manufacturing facility in Newport, we are pleased to announce that we are nearing completion of the expansion space fit out for the site.


Commissioning and final fix to the laboratory assembly areas and ISO 6 cleanrooms are well underway and the new Plantroom is proving a great example of modular design and off-site fabrication. From the upfront Plantroom BIM model coordination to the time efficiency of delivery/installation leading seamlessly to System flushing, we are delighted with the progress so far and are looking forward to the forthcoming handover.