After the first month on site, works on the SPTS fit out for KLA is progressing at pace, with the newly established SUB FAB area taking shape on schedule and progress being made in the manufacturing Hall, where HL ceiling brackets and M&E install is advancing alongside floor preparation and sealing works.
We have also commenced work on the first-floor cleanroom and expansion spaces, looking ahead to the next four weeks of deliveries and sub-contractor engagement in preparation for the start of the Gas Bunker build works.
Full credit to the onsite team at SPTS who have proved that with detailed planning and coordination between trades, a site can operate as a clean, efficient and most importantly, a safe working environment.
Thank you also to Kernow Fixings who have worked with us on this project providing the bracketry for the Sub Fab.